| Bridges Reconstruction Status |
|
|
| (List prepared by
Recovery Unit - Presidency of the Council of Ministers |
|
|
|
|
|
|
27/12/2007 |
|
Total No. of
Bridges Destroyed is 91 |
91 Bridges Are donated |
76 Bridges
Completed |
|
|
|
|
46 with
( MPW) & 45 with (CDR) |
0 Bridges Are Undonated |
15
Bridges Uncompleted |
|
|
|
|
|
|
|
|
| |
MPW ReferenceNo. |
Location |
Bridge Name |
Donor |
Construction
Progress % |
|
|
| 1 |
39 |
South |
Hajje |
Under Higher Council
for Relief and MPW |
100% |
|
|
| 2 |
40 |
South |
Hajje Maamariye |
Iran |
100% |
|
|
| 3 |
|
South |
KAKAIEH |
Iran |
100% |
|
| 4 |
|
South |
Mliekh Bridge |
Iran |
Design stage |
|
| 5 |
118 |
South |
Jbal lbotm Bridge |
Under Higher Council
for Relief and MPW |
100% |
|
| 6 |
99 |
South |
Jouaya to Tyre |
Under Higher Council
for Relief and MPW |
100% |
|
| 7 |
49 |
South |
Sarafand over Qassmieh
ditch |
Higher council of
Relief |
100% |
|
| 8 |
50 |
South |
Saksakieh small culvert |
Higher council of
Relief |
100% |
|
| 9 |
43 |
South |
Tair Falsay - Six February
Bridge over Nahr Al Litani |
Zrariyeh Municipality
Mayor |
100% |
|
| 10 |
142 |
South |
Bqosta |
Russia (Permanent
Steel Bridge) |
100% |
|
| 11 |
29 |
South |
Qasimye Bridge (East) |
Hjeij |
100% |
|
| 12 |
98 |
South |
Mafraq Deir Antar Bridge |
Hjeij |
100% |
|
| 13 |
69 |
South |
Ramp to Saida East
Boulevard |
Mr. Saad El Hariri |
100% |
|
| 14 |
107 |
South |
Owali Bridge |
Mr. Saad El Hariri |
100% |
|
| 15 |
106 |
South |
Sainiq |
Mr. Saad El Hariri |
100% |
|
| 16 |
71 |
South |
Ghaziyeh OverPass |
Mr. Bahaa El Hariri |
100% |
|
| 17 |
70 |
South |
Qinnarit OverPass |
Mr. Bahaa El Hariri |
100% |
|
| 18 |
89-90-139 |
South |
Zahrani Interchange to
Nabatiyeh |
Mr. Bahaa El Hariri |
100% |
|
| 19 |
95 |
South |
Old road Zahrani Bridge
over the river |
Mr. Bahaa El Hariri |
100% |
|
| 20 |
105 |
South |
PS 1 - Addousiyeh OverPass
1.8km south of Zahrani |
Iran |
100% |
|
| 21 |
104 |
South |
PS3 - Sarafand OverPass
6.5km south of Zahrani |
Iran |
100% |
|
| 22 |
138 |
South |
PS4 - Babliyeh Interchange
OverPass 7.75km south of Zahrani |
Iran |
100% |
|
| 23 |
143 |
South |
PS4 bis - Saksakiyeh
OverPass 8.2km south of Zahrani |
Iran |
100% |
|
| 24 |
103 |
South |
V3 - Khayzaran Viaduct |
Iran |
100% |
|
| 25 |
136 |
South |
PI 3 - Ansariyeh UnderPass
10+050km south of Zahrani |
Iran |
100% |
|
| 26 |
135 |
South |
PI 4 - Ansariyeh Deir Takla UnerPass 10+700km
south of Zahrani |
Iran |
100% |
|
| 27 |
137 |
South |
PI 6 - Abou El Aswad
UnderPass 15+400km south of Zahrani |
Iran |
100% |
|
| 28 |
23 |
South |
Qasmiyeh on Int'l Road - 1 |
Hjeij |
100% |
|
| 29 |
96 |
South |
Culvert over water way near
Bayadah |
Kingdom
of Saudi Arabia |
100% |
|
|
|
|
|
|
|
|
|
South |
12 Bridges With The Ministry of Public Works (MWP) |
|
|
|
|
|
South |
17 Bridges
With The Council for Development & Reconstruction (CDR) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
MPW ReferenceNo. |
Location |
Bridge Name |
Donor |
Construction
Progress % |
|
| 1 |
120 |
Nabatiye |
Wazani Bridge |
Iran |
95% |
|
| 2 |
121 |
Nabatiye |
El Mari Bridge |
Iran |
Design stage |
|
| 3 |
4 |
Nabatiye |
Abou Zemle (Al Ghajar) |
Islamic Development
Bank |
30% |
|
| 4 |
122 |
Nabatiye |
Fardis Bridge |
Iran |
80% |
|
| 5 |
123 |
Nabatiye |
Zaghla Bridge |
Iran |
100% |
|
| 6 |
140 |
Nabatiye |
ROUMINE - Deir Ezzahrani |
Under Higher Council
for Relief and MPW |
100% |
|
| 7 |
134 |
Nabatiye |
Wadi elakhdar/Arbsalim/Kfar
Remman |
Iran |
95% |
|
| 8 |
125 |
Nabatiye |
Tahrir |
Amal Hourani |
100% |
|
| 9 |
13 |
Nabatiye |
Habbouch - Aarabsalim |
Ali Ahmad Farhat |
100% |
|
| 10 |
119 |
Nabatiye |
qaaqaeit aljisr |
Hjeij |
100% |
|
| 11 |
17 |
Nabatiye |
Khardali Bridge |
Hjeij |
100% |
|
| 12 |
91 |
Nabatiye |
Habboush OverPass |
Fawzi Jaber Sons |
100% |
|
| 13 |
92 |
Nabatiye |
Habboush UnderPass |
Under Higher Council
for Relief and MPW |
100% |
|
| 14 |
144 |
Nabatiye |
Kfarmashkeh - Hasbayah -
box culvert 1 at 12+600 |
Under MPW ongoing
Project |
100% |
|
| 15 |
|
Nabatiye |
Hassbani Bridge (Abou Wadih) |
Hjeij |
100% |
|
| 16 |
145 |
Nabatiye |
Kfarmeshkeh - Hasbayah -
box culvert 2 at 12+050 |
Under MPW ongoing
Project |
100% |
|
|
|
|
|
|
|
Nabatiye |
16 Bridges With The Ministry of Public Works (MWP) |
|
|
|
Nabatiye |
0 Bridges With
The Council for Development & Reconstruction (CDR) |
|
|
|
|
|
|
|
|
|
| |
MPW ReferenceNo. |
Location |
Bridge Name |
Donor |
Construction
Progress % |
|
| 1 |
88 |
Mount Lebanon |
Baabda |
World Bank |
Being Contracted |
|
| 2 |
79 |
Mount Lebanon |
Ghariefa Bridge |
Under Higher Council
for Relief and MPW |
100% |
|
| 3 |
115-116 |
Mount Lebanon |
Hazmiyeh - Airport road
Viaduct 1 - 2(Section B |
Kingdom of Saudi
Arabia |
100% |
|
| 4 |
117 |
Mount Lebanon |
Old Airport Road Bridge |
Under contruction by
CDR / UTDP |
10% |
|
| 5 |
53 |
Mount Lebanon |
Ouzaii highway of airport |
Under Construction by
Airport Authority |
100% |
|
| 6 |
141 |
Mount Lebanon |
Sofar Viaduct |
Italy |
Design Finalized |
|
| 7 |
74 |
Mount Lebanon |
Mdeirej Viaduct |
USAID |
13% |
|
| 8 |
55 |
Mount Lebanon |
Old Naameh UnderPass |
Mr. Saad El Hariri |
100% |
|
| 9 |
56 |
Mount Lebanon |
Naameh Interchange overpass |
Mr. Saad El Hariri |
100% |
|
| 10 |
57 |
Mount Lebanon |
Bridge South Pedeterian
OverPass (Haret el Rouss) |
Kingdom of Saudi
Arabia |
|
|
| 11 |
58 |
Mount Lebanon |
Damour-Oceana Beach Bridge |
Mr. Nehmeh Tohmeh |
100% |
|
| 12 |
59 |
Mount Lebanon |
Bridge North of Chouf
Interchange (neatr Ministry of Displaced) |
Kingdom of Saudi
Arabia |
Being Contracted |
|
| 13 |
60 |
Mount Lebanon |
Chouf Interchange |
Mr. Saad El Hariri |
100% |
|
| 14 |
51 |
Mount Lebanon |
Old Damour Bridge |
Kingdom of Saudi
Arabia |
15% |
|
| 15 |
61 |
Mount Lebanon |
Damour Bridge |
Kingdom of Saudi
Arabia |
100% |
|
| 16 |
68 |
Mount Lebanon |
Jissr Beach Bridge |
Kingdom of Saudi
Arabia |
Design stage |
|
| 17 |
62 |
Mount Lebanon |
El Debiyeh Underpass |
Mr. Saad El Hariri |
100% |
|
| 18 |
63 |
Mount Lebanon |
OverPass South of Aytman
Gaz Station |
Mr. Mayssara Succar |
100% |
|
| 19 |
64 |
Mount Lebanon |
Jieh OverPass - North of
Jammoul Bakery |
Mr. Mayssara Succar |
100% |
|
| 20 |
66 |
Mount Lebanon |
Wadi El Zayneh Viaduct |
Kingdom of Saudi
Arabia |
100% |
|
| 21 |
72 |
Mount Lebanon |
Wardaniyeh Interchange -
PS4 |
Mr. Bahaa El Hariri |
100% |
|
| 22 |
73 |
Mount Lebanon |
Rmeileh OverPass - PS5 |
Mr. Bahaa El Hariri |
100% |
|
| 23 |
67 |
Mount Lebanon |
Rmeileh / Olman Interchange |
Mr. Saad El Hariri |
100% |
|
| 24 |
130 |
Mount Lebanon |
Ghazir Bridge |
Frem Institution |
100% |
|
| 25 |
33 |
Mount Lebanon |
Maameltein - Casino Bridge |
Casino du Liban |
100% |
|
| 26 |
37 |
Mount Lebanon |
El Fidar Bridge |
Byblos Bank |
100% |
|
|
|
|
|
Mount Lebanon |
3 Bridges With The Ministry of Public Works (MWP) |
|
|
Mount Lebanon |
23 Bridges
With The Council for Development & Reconstruction (CDR) |
|
|
|
|
|
|
|
| |
MPW ReferenceNo. |
Location |
Bridge Name |
Donor |
Construction
Progress % |
|
| 1 |
126 |
Bekaa |
Qaa Culvert (Gov. Hospital) |
Under Higher Council
for Relief and MPW |
100% |
|
| 2 |
131 |
Bekaa |
Bednayel bridge |
Under Higher Council
for Relief and MPW |
100% |
|
| 3 |
128 |
Bekaa |
zaarourieh -allek |
Under Higher Council
for Relief and MPW |
100% |
|
| 4 |
129 |
Bekaa |
saaydeh - majdaloun |
Under Higher Council
for Relief and MPW |
100% |
|
| 5 |
114 |
Bekaa |
Riyaq Rail road bridge over
Nahr al Litani |
Greece |
being contracted |
|
| 6 |
80 |
Bekaa |
Alassi Bridge |
Iran |
100% |
|
| 7 |
124 |
Bekaa |
Fersol - Jarmashiyeh |
Mr. Saad El Hariri |
100% |
|
| 8 |
113 |
Bekaa |
Bridge between Tirbil &
Firzil |
Delta Trading |
100% |
|
| 9 |
133 |
Bekaa |
Taanael - Barr Elias near
Alba |
Mr. Saad El Hariri |
100% |
|
| 10 |
86 |
Bekaa |
Al Sahel - Ras Baalbeck |
Under Higher Council
for Relief and MPW |
100% |
|
| 11 |
77 |
Bekaa |
Ablah - Baalbak - tel
Aamara |
Mr. Saad El Hariri |
100% |
|
|
|
|
|
|
Bekaa |
9 Bridges With The Ministry of Public Works (MWP) |
|
|
Bekaa |
2 Bridges With
The Council for Development & Reconstruction (CDR) |
|
|
|
|
| |
MPW ReferenceNo. |
Location |
Bridge Name |
Donor |
Construction
Progress % |
|
| 1 |
85 |
North |
Hissa Ballaneh |
Mr. Ahmad Trad |
100% |
|
| 2 |
93 |
North |
Kbayet
Akkar |
Under Higher Council
for Relief and MPW |
100% |
|
| 3 |
48 |
North |
Mazraat Balde&Kafar
Harra (Swaysseh) |
Mr. Saad El Hariri |
100% |
|
| 4 |
34 |
North |
Kouwaikhat |
Mr. Saad El Hariri |
100% |
|
| 5 |
35 |
North |
Aawik Halba |
Mr. Saad El Hariri |
100% |
|
| 6 |
127 |
North |
Arqa Bridge |
Mr. Saad El Hariri |
100% |
|
| 7 |
36 |
North |
Madfoun Bridge |
Mr. Najib Mikati |
100% |
|
| 8 |
81 |
North |
Arqa coastal Bridge |
Mr. Saad El Hariri |
100% |
|
| 9 |
|
North |
Qlaiaat Airport Bridge |
Kingdom
of Saudi Arabia |
100% |
|
|
|
|
|
North |
6 Bridges With The Ministry of Public Works (MWP) |
|
|
North |
3 Bridges With
The Council for Development & Reconstruction (CDR) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|